Job cost detail

Budget, committed and actual cost for every phase and cost code with activity, and what is left. Filtered to J-1003 Turtle Back Zoo – Lemur Exhibit.

12 rows

Budget, committed and actual by phase
Structural & Building Construction
$800,000.00
$550,000.00
$0.00
Mechanical & Electrical
$650,000.00
$570,000.00
$0.00
Building Envelope & Finishes
$600,000.00
$0.00
$0.00
Site Work & Preparation
$600,000.00
$450,000.00
$30,500.00
Labor & Equipment
$450,000.00
$0.00
$10,685.60
  • Budget
  • Committed
  • Actual
JobNamePhaseCost codeDescriptionCategoryBudgetCommittedActualRemaining% used
J-1003Turtle Back Zoo – Lemur ExhibitBuilding Envelope & Finishes07-000Thermal & Moisturematerials$200,000.00$0.00$0.00$200,000.000.0%
J-1003Turtle Back Zoo – Lemur ExhibitBuilding Envelope & Finishes08-000Doors & Windowsmaterials$150,000.00$0.00$0.00$150,000.000.0%
J-1003Turtle Back Zoo – Lemur ExhibitBuilding Envelope & Finishes09-000Finishesmaterials$250,000.00$0.00$0.00$250,000.000.0%
J-1003Turtle Back Zoo – Lemur ExhibitLabor & Equipment90-100Laborlabor$300,000.00$0.00$1,185.60$298,814.400.4%
J-1003Turtle Back Zoo – Lemur ExhibitLabor & Equipment90-200Equipment Rentalequipment$150,000.00$0.00$9,500.00$140,500.006.3%
J-1003Turtle Back Zoo – Lemur ExhibitMechanical & Electrical15-000Mechanicalsubs$350,000.00$290,000.00$0.00$60,000.0082.9%
J-1003Turtle Back Zoo – Lemur ExhibitMechanical & Electrical16-000Electricalsubs$300,000.00$280,000.00$0.00$20,000.0093.3%
J-1003Turtle Back Zoo – Lemur ExhibitSite Work & Preparation01-000General Requirementsother$0.00$0.00$30,500.00-$30,500.00—
J-1003Turtle Back Zoo – Lemur ExhibitSite Work & Preparation02-000Site Worksubs$600,000.00$450,000.00$0.00$150,000.0075.0%
J-1003Turtle Back Zoo – Lemur ExhibitStructural & Building Construction03-000Concretematerials$350,000.00$325,000.00$0.00$25,000.0092.9%
J-1003Turtle Back Zoo – Lemur ExhibitStructural & Building Construction05-000Metalsmaterials$275,000.00$225,000.00$0.00$50,000.0081.8%
J-1003Turtle Back Zoo – Lemur ExhibitStructural & Building Construction06-000Wood & Plasticsmaterials$175,000.00$0.00$0.00$175,000.000.0%
Total$3,100,000.00$1,570,000.00$41,185.60$1,488,814.40