Job cost detail

Budget, committed and actual cost for every phase and cost code with activity, and what is left. Filtered to J-1001 Riverside Elementary Gym Renovation.

6 rows

Budget, committed and actual by phase
Structure
$67,200.00
$15,800.00
$18,400.00
Finishes
$58,500.00
$16,250.00
$9,750.00
Demolition
$18,000.00
$0.00
$5,116.40
  • Budget
  • Committed
  • Actual
JobNamePhaseCost codeDescriptionCategoryBudgetCommittedActualRemaining% used
J-1001Riverside Elementary Gym RenovationDemolition02-000Site Worksubs$12,000.00$0.00$2,350.00$9,650.0019.6%
J-1001Riverside Elementary Gym RenovationDemolition90-100Laborlabor$6,000.00$0.00$2,766.40$3,233.6046.1%
J-1001Riverside Elementary Gym RenovationFinishes09-000Finishesmaterials$31,000.00$0.00$0.00$31,000.000.0%
J-1001Riverside Elementary Gym RenovationFinishes16-000Electricalsubs$27,500.00$16,250.00$9,750.00$1,500.0094.5%
J-1001Riverside Elementary Gym RenovationStructure03-000Concretematerials$38,000.00$15,800.00$18,400.00$3,800.0090.0%
J-1001Riverside Elementary Gym RenovationStructure05-000Metalsmaterials$29,200.00$0.00$0.00$29,200.000.0%
Total$143,700.00$32,050.00$33,266.40$78,383.60