| Cost code | Budget | Committed | Actual | Remaining | |
|---|---|---|---|---|---|
Demolition | |||||
| 02-000 Site Work | $ | $0.00 | $2,350.00 | $9,650.00 | |
| 90-100 Labor | $ | $0.00 | $2,766.40 | $3,233.60 | |
$ | |||||
Structure | |||||
| 03-000 Concrete | $ | $15,800.00 | $18,400.00 | $3,800.00 | |
| 05-000 Metals | $ | $0.00 | $0.00 | $29,200.00 | |
$ | |||||
Finishes | |||||
| 09-000 Finishes | $ | $0.00 | $0.00 | $31,000.00 | |
| 16-000 Electrical | $ | $16,250.00 | $9,750.00 | $1,500.00 | |
$ | |||||
| Total | $138,500.00 | $32,050.00 | $33,266.40 | $78,383.60 | |