J-1001 Riverside Elementary Gym Renovation

INV-1001

PaidProgress billing #1 · Riverside School District

Dated 2026-09-01 · due 2026-10-01 · period to 2026-08-31 · sent

DescriptionScheduledThis period
Demolition & prep$30,000.00$30,000.00
Structure$70,000.00$20,000.00
Finishes$84,500.00$0.00
Billed
$50,000.00
Retainage (10%)
-$5,000.00
Amount due
$45,000.00
Paid
$45,000.00
Balance
$0.00

Application summary (G702)

1 Original contract sum
$184,500.00
2 Net change by change orders
$6,800.00
3 Contract sum to date
$191,300.00
4 Completed and stored to date
$50,000.00
5 Retainage
$5,000.00
6 Earned less retainage
$45,000.00
7 Previous certificates
$0.00
8 Current payment due
$45,000.00
9 Balance to finish
$146,300.00

The PDF adds the G703 continuation sheet.

Payments

ReceivedMethodReferenceAmount
2026-09-10CheckCheck 20418$45,000.00
INV-1001 · Prophic